Execution

Beiztechnik co-ordinates all cleaning tasks. However, to achieve a smooth execution, Site staff support is mandatory as they understand the site construction setup and Beiztechnik cannot involve themselves in all subsystems for the limited time of the cleaning.

The actual on site cleaning tasks depend on the complexity of the job and may take between two days to a maximum of two weeks. The evaluation and acceptance of the clean will be controlled by a local visual inspection of accessible components by all concerned parties. A cleaning report shows the following minimum details. boiler technical details, treatment steps, chemical analysis by system, chemical inventory, water usage and chemical treatment and disposal.